Project Timeline

  • Construction phase

Scope of Work

    • Replace the current building with four small schools: PreK-3, 4-8, and two small high schools
    • Career training area
    • Student and community center with a gym and performing arts space
    • A portion of this project is an alternate for BEST funding

Global Intermediate (4-8) Construction Updates

  • UPDATE – Nov. 1, 2019

    Posted by Andy Leapley on 11/1/2019
    • The erection of structural steel is now complete throughout the building. 
    • Crews have begun to pour slab-on-grade for the second floor and will soon begin on the classroom wing. 
    • To combat the weather, waterproof paneling now surrounds the building.  
    Comments (-1)
  • UPDATE – Oct. 17, 2019

    Posted by Andy Leapley on 10/17/2019
    •  Structural steel placement is wrapping up this week with only minor details remaining.
    • Braces for the classroom precast has been removed, allowing crews to begin backfilling.
    • Next week, crews will pour decking on the second floor.
    • Once the structural steel is complete, the crews will move inside for framing the classrooms and hallways!
    Comments (-1)
  • UPDATE – Oct. 11, 2019

    Posted by Andy Leapley on 10/11/2019
    • Precast concrete panel installation is complete. 
    • Structural steel placement is mostly complete throughout the structure. 
    • Installation of floor decking is in-process. 
    • Concrete slab on grade pours is scheduled for the beginning of October. 
    • Completion is expected for school to open the fall of 2020. 
    Comments (-1)